Chisholm School District Demolition
Demolition of a 115,800-square-foot, three-story elementary school and below-grade boiler house, including the removal and recycling of more than 10,500 tons of material.
The Project
Landwehr Construction completed the demolition of the former elementary school and boiler house for the Chisholm School District in Chisholm, Minnesota. Located in northern Minnesota’s Iron Range, the project involved the removal of a three-story, 115,800-square-foot school building standing approximately 45 feet tall, along with a boiler house extending approximately 15 feet below grade.
The project presented a demanding summer construction schedule as demolition could not begin until students were out of school, and the site needed to be cleared, regraded, and paved before the start of the next school year in the fall.
The Solution
To meet the five-week project schedule, Landwehr deployed three excavators, including its new high-reach demolition excavator in a mid-reach configuration. With a 53-foot working reach and the ability to handle tools weighing up to 9,920 pounds, the equipment gave the crew a significant productivity advantage by bringing down the three-story school building in a matter of days rather than weeks.
The demolition also generated approximately 10,500 tons of material, including 4,000 tons of concrete. Concrete and structural steel were recycled offsite through local businesses.