Barnes County, ND Box Culvert Replacement

Landwehr served as prime contractor for the two-year North Dakota Department of Transportation (NDDOT) Box Culvert Replacement Project in Valley City, ND, one of our largest culvert projects to date.

 

 

20240912 154000949 Ios (1)

The Project

The existing culvert had deteriorated and needed to be replaced. The work also included improving the surrounding roadways and utilities, while managing contaminated water and soils and building to North Dakota’s construction specifications.

20240628 202458081 Ios (1)

The Solution

As the prime contractor, Landwehr handled the full scope:

  • Installed 1,703 feet of 10′ x 7′ box culvert, including two curved sections
  • Installed 1,700 feet of new water main
  • Built a $400,000 concrete outlet structure
  • Rebuilt 3,400 feet of frontage road
  • Re-ditched 600 feet
  • Reconstructed 0.35 miles of road, with 0.2 miles of mill and fill resurfacing
  • Plugged the deteriorated pipe with 12,000 CY of concrete

 

The project finished eight months ahead of schedule and without interruptions to businesses.