George’s Ballroom Demolition

Demolition of the 32,000-square-foot ballroom, including hazardous material abatement, materials sorting and recycling, and preservation of the building’s marquee sign.

Img 4113 2

The Project

Landwehr’s demolition crew took down George’s Ballroom, a New Ulm landmark since the 1940s. After the building sat vacant for more than 30 years, decades of decay and deferred maintenance had left it unsalvageable, with asbestos present throughout, adding complexity to the demolition and material handling process. The crew worked with dust suppression equipment throughout the project to control airborne particles and completed the demolition in roughly three weeks, despite the added precautions.  

Demolition Truck Loaded With Scrap Metal And Debris

The Solution

The crew sorted demolition materials throughout the project, recycling 135 tons of steel, iron, and copper along with 2,000 tons of concrete. The building’s marquee sign was carefully preserved, ensuring a piece of the community’s history is carried forward into the site’s next chapter. 

Ready to Work Together?

Tell us about your project, and we’ll connect you with the right team.