Highway 10 & 23 Interchange Reconstruction

Full reconstruction of the Highway 10 & 23 interchange for MNDOT, including three bridges, interchange regrading, utility and pipe work, paving, and signal and lighting systems.

Project Snapshot

85,000

Tons of removal

40,000

Linear feet of pipe

500,000

Cubic yards of earthwork

2.5 miles

Of 4-lane concrete paving

Default

The Project

As Landwehr’s largest company project to date, this two-year reconstruction rebuilt one of St. Cloud’s busiest interchanges for MNDOT, the City of St. Cloud, and Benton County. The project replaced Highway 23 bridges and redesigned the interchange from an eight-ramp layout to a more efficient four-ramp folded diamond configuration, along with a new Fourth Street Southeast bridge over Highway 10.

Picture1

The Solution

With traffic volumes on Highway 23 exceeding 26,000 vehicles a day, the project required extensive phasing and subcontractor coordination to keep the corridor moving throughout construction. The completed interchange was recognized with a performance award from MNDOT. 